Contract 76916 REL 12: 2002-011-00 EXP KOOTENAI RIVER OPERATIONAL LOSS ASSESSMENT
Project Number:
Title:
Kootenai River Floodplain Ecosystem Operational Loss Assessment, Protection, Mitigation and Rehabilitation Project
Stage:
Implementation
Area:
Province Subbasin %
Mountain Columbia Kootenai 100.00%
Contract Number:
76916 REL 12
Contract Title:
2002-011-00 EXP KOOTENAI RIVER OPERATIONAL LOSS ASSESSMENT
Contract Continuation:
Previous: Next:
76916 REL 7: 2002-011-00 EXP KOOTENAI RIVER OPERATIONAL LOSS ASSESSMENT MT
  • 76916 REL 20: 2002-011-00 EXP KOOTENAI RIVER OPERATIONAL LOSS ASSESSMENT
Contract Status:
Closed
Contract Description:
Under this contract, Montana Fish, Wildlife and Parks will continue, in partnership and coordination with the Kootenai Tribe of Idaho, to implement the Operational Loss Assessment and the Kootenai River Operational Mitigation and Evaluation Plan on the Montana portion of the Kootenai River floodplain by identifying, designing, and implementing management actions that offset wildlife impacts caused by the operation of Libby Dam. Those impacts are described in the Kootenai River Floodplain Ecosystem Operational Loss Assessment Report (2013) and the mitigation actions are described in the Kootenai River Floodplain Ecosystem Operational Mitigation and Evaluation (KROME) Plan (2016).
Account Type(s):
Expense
Contract Start Date:
07/01/2020
Contract End Date:
06/30/2021
Current Contract Value:
$121,089
Expenditures:
$121,089

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Caryn Dearing Montana Fish, Wildlife and Parks (MFWP) No Administrative Contact cdearing@mt.gov (406) 444-3677
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Chris Hammond Montana Fish, Wildlife and Parks (MFWP) Yes Supervisor chammond@mt.gov (406) 751-4595
Lena Havron Montana Fish, Wildlife and Parks (MFWP) No Administrative Contact Lena.Havron@mt.gov (406) 444-4629
Franz Ingelfinger Montana Fish, Wildlife and Parks (MFWP) Yes Contract Manager fingelfinger@mt.gov (406) 751-4580
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Kris Tempel Montana Fish, Wildlife and Parks (MFWP) Yes Technical Contact ktempel@mt.gov (406) 751-4573
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Oversight and Administer Planning and Design and New Project Activities 06/30/2021 06/29/2021
Basinwide Coordination C: 189. Planning, Design & Coordination of Existing & New Projects 06/30/2021 06/29/2021
Maintain Restoration Plantings D: 198. Maintenance of Dunn Creek Restoration Planting 06/30/2021 06/29/2021
Completed Environmental Compliance E: 165. Complete Environmental Clearance Measures for Floodplain Enhancement at Wild River 06/30/2021
Wild River Restoration Design F: 175. Wild River Restoration 06/30/2021 06/29/2021
Complete Environmental Compliance G: 165. Complete EC documents for Yaak Confluence Floodplain Enhancement 06/30/2021 06/29/2021
Yaak River Confluence Restoration Design H: 175. Yaak River Confluence Restoration 06/30/2021 06/29/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Oversight and Administer Planning and Design and New Project Activities
C 189 Planning, Design & Coordination of Existing & New Projects
D 198 Maintenance of Dunn Creek Restoration Planting 06/28/2021
E 165 Complete Environmental Clearance Measures for Floodplain Enhancement at Wild River
F 175 Wild River Restoration
G 165 Complete EC documents for Yaak Confluence Floodplain Enhancement
H 175 Yaak River Confluence Restoration
I 132 No Annual Report